Manhole Cover Refurb

Case Study - Manhole Cover Refurb

Case Study - Manhole refurbishment

Location
Civil works

Issue
Eroded chemical contaminated manhole. Proximity to very old buildings prevented excavation in order to replace.

Our provided solution
Over pumping was installed, and manhole blasted to ensure that a sound surface was evident which was subsequently cleaned prior to further refurbishment.

Manhole was re-faced, benching was re-built and the fitting of a brand new cover slab and lining with thermosetting plastic coating.

We ensured that minimum disruption was caused and manhole was back online within a 2 day period.

Case Study Manhole (Before)

State of manhole prior refurb

Case Study Manhole (After)

Manhole following refurb (2 days)